Corporate law Brisbane

Failure to review contracts can cost millions…

HomePrivate: BlogCommercial lawCorporate lawFailure to review contracts can cost millions…

by

reviewed by

Malcolm Burrows

The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Employsure’s Google Ads found to mislead businesses

    Employsure’s Google Ads found to mislead businesses

    The Australian Competition and Consumer Commission’s (ACCC) appeal against Employsure Pty Ltd has been upheld by the Full Federal Court. Find out what this means for Australian consumers and businesses and how it could affect the future of consumer law.

    Read more …

  • Data breach compliance and response plans

    Data breach compliance and response plans

    Dundas Lawyers create tailored data breach response plans to ensure compliance with the Privacy Act 1988 (Cth). Plans include actions, registers, records, tests and tasks. Get an obligation-free and confidential discussion to learn more.

    Read more …

  • Case study – intellectual property protection structures

    Case study – intellectual property protection structures

    Protect your valuable intellectual property and secure revenue for product development. Learn how Dundas Lawyers can help you create an intellectual property protection structure with potential benefits for your business.

    Read more …

  • Negotiating and formalising a joint venture

    Negotiating and formalising a joint venture

    Forming a successful joint venture requires careful consideration of multiple factors. This article outlines the necessary elements and provides an ideal structure to help you get started. Learn more about what it takes to create a successful joint venture.

    Read more …

  • Injunction sought for breach of confidence

    Injunction sought for breach of confidence

    Dundas Lawyers helped a corporate client protect their confidential information and copyright material from a former employee and contractor. Read the full article to learn how they used detailed work and a chronology to secure justice for their client.

    Read more …

  • Are email trackers admissible as evidence?

    Are email trackers admissible as evidence?

    The Evidence Act 1995 (Cth) is silent, but the Court considers email trackers and read receipts as evidence in civil and intellectual property litigation. As seen in Jaffari v Grabowski [2013] NSWCA 114, sender’s receipt of confirmation of email relay is a matter for the recipient.

    Read more …

  • COVID-era electronic signing of documents to continue

    COVID-era electronic signing of documents to continue

    The Treasury Laws Amendment Bill 2021 gives companies the power to conduct business virtually, with the ability to execute documents electronically, hold virtual meetings, and maintain electronic minute books. A practical solution to pandemic-related challenges.

    Read more …

  • QBCC Home Warranty Insurance Claims – pt 4

    QBCC Home Warranty Insurance Claims – pt 4

    In Schneider v Queensland Building and Construction Commission [2021] QCA 155, the Court of Appeal held that the QBCC Home Warranty Insurance Scheme does not extend to prepayments for residential construction work yet to be performed. Read Dundas Lawyers’ article to learn more.

    Read more …

  • A test for the infringement of circuit layout rights

    A test for the infringement of circuit layout rights

    This article explores the legal implications of circuit layouts, such as what qualifies as an eligible layout, the exclusive rights granted, and exceptions to infringement. Learn more by reading the case of Lumen Australia Pty Ltd v Frontline Australasia Pty Ltd [2018] FCA 1807, discussed in the article.

    Read more …


Posted

in

, ,
Send this to a friend