The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • The running account defence to unfair preference claims

    The running account defence to unfair preference claims

    Creditors who have been paid by a customer on credit may find themselves facing an Unfair Preference claim letter from a liquidator. Learn more about the defences available to creditors and how to protect yourself from repaying more than your fair share.

    Read more …

  • Legal risks of unlicensed building work

    Legal risks of unlicensed building work

    Unlicensed building work in Queensland can have serious consequences. Find out more about the potential penalties and exceptions in this article.

    Read more …

  • Confusing marks – Sensis v Senses

    Sensis Pty Ltd v Senses Direct Mail and Fulfillment Pty Ltd [2019] FCA 719: Court ruled SENSES marks deceptively similar to SENSIS marks, highlighting importance of engaging intellectual property lawyers when building a brand. Marks can be infringing if spelling is only slightly different, if it resembles another and likely to deceive and cause confusion.

    Read more …

  • Unfair preferences & the set-off defence

    Unfair preferences & the set-off defence

    Under section 588FA of the Corporations Act 2001 (Cth) (Act) an unfair preference is defined as a transaction, such as payment of an outstanding debt, between a company and an unsecured creditor which results in that unsecured creditor receiving more than it would have received if it had to prove in the winding up of the…

    Read more …

  • Construction contracts: addressing defects and final stages

    Construction contracts: addressing defects and final stages

    Terminating a residential construction contract can be risky. Learn how to avoid costly litigation outcomes and understand the full implications of termination before taking action.

    Read more …

  • Contractual terms can be misleading – Jetstar under fire

    Contractual terms can be misleading – Jetstar under fire

    Jetstar Airways Pty Ltd has been found to have breached the Australian Consumer Law. Find out what this means for other companies and how to protect your business.

    Read more …

  • Technology startups – top 5 legal considerations

    Technology startups – top 5 legal considerations

    Start your tech startup on the right footing by considering the top five (5) legal considerations: entity structure and asset protection, intellectual property (IP), confidentiality, contracts, privacy and compliance.

    Read more …

  • Need a reseller agreement?

    Need a reseller agreement?

    This article provides an overview of the considerations when entering into a Joint Venture, including inputs, outputs, legal and tax implications of different Joint Venture vehicles. Get the facts you need to make an informed decision.

    Read more …

  • Legal concerns in software support agreements

    Legal concerns in software support agreements

    Software developers must consider tech and product support services when taking software to market, such as differences between technical and product support, supported and non-supported items, and differences between installed and hosted software support agreements.

    Read more …


Posted

in

, ,
Send this to a friend