The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Arbitration clauses in international contracts

    Arbitration clauses in international contracts

    Arbitration is a private process where parties to a commercial contract agree (Arbitration Agreement) to let an arbitrator[1] (Arbitrator) make a binding decision on a dispute between them, without recourse to national Courts.  The Arbitrator receives evidence, hears arguments and applies relevant law to reach a binding decision, called an award (Award).  The Arbitrator’s decision…

    Read more …

  • Tortious contract interference – injunctive relief

    Tortious contract interference – injunctive relief

    The wrongful or “tortious” interference with a contract occurs when a third party intentionally causes a contracting party to commit a breach of contract.  The third party will be liable if they intentionally induced or disrupted a party’s ability to perform the terms of a binding contract.  Remedies for tortious interference are available to ensure…

    Read more …

  • Misuse of confidential information within source code

    Misuse of confidential information within source code

    In Australia, computer code can amount to confidential information as well as being subject to copyright protection.  In some cases the two things overlap as was the case in decision of the Court in Optus Networks Pty Ltd v Telstra Corporation Ltd (2010) 265 ALR 281; [2010] FCAFC 21.

    Read more …

  • Are contract recitals legally binding?

    Are contract recitals legally binding?

    Recitals, also known as the “preamble” or “details” clauses (Recitals) are introductory statements at the start of a contract that provide context, background or reasons for the terms and conditions that follow.  They have been historically used by the Courts to aid in the interpretation of ambiguous terms and are capable of including essential provisions…

    Read more …

  • Compensation and breaches of directors’ duties

    Compensation and breaches of directors’ duties

    Should it be held that a director of a company has breached their statutory duties, as contained in the Corporations Act 2001 (Cth) (Act), then the question arises as to how a Court will determine the amount of compensation to be paid by the errant director.  The remedies provided for in the Act include declaratory…

    Read more …

  • IP Australia follows Madrid Goods and Services list

    IP Australia follows Madrid Goods and Services list

    From 26 March 2024, IP Australia has implemented the internationally recognised Madrid Goods and Services list (Madrid List), replacing the AU Goods and Services Picklist.[1]  The adoption of the Madrid List comes as Intellectual Property Australia (IP Australia) seeks to align the Australian classification standards with the other intellectual property offices around the world.

    Read more …

  • The “right to disconnect” from modern workplaces

    The “right to disconnect” from modern workplaces

    The right to disconnect, as contained in Part 8 of the  Fair Work Amendment (Closing Loopholes No. 2) Bill (Bill), gives employees the right to refuse contact from their employers (or related parties) outside of their working hours, unless the refusal is unreasonable.  The changes in Part 8 amend various sections of the Fair Work…

    Read more …

  • Provisional liquidators in shareholder disputes

    Provisional liquidators in shareholder disputes

    The appointment of a provisional liquidator may be appropriate in shareholder disputes if there are genuine concerns that there is a risk a company’s assets will be dissipated, there are potential solvency concerns and all other alternatives have been exhausted.  The appointment of a provisional liquidator by a Court has been said to be ‘a…

    Read more …

  • Top stoic quotes from Justice Lee in Lehrmann v Network Ten

    Top stoic quotes from Justice Lee in Lehrmann v Network Ten

    On 15 April 2024 Justice Lee handed down his decision in the case of Lehrmann v Network Ten Pty Limited (Trial Judgment) [2024] FCA 369.  This matter has attracted a large amount of media attention and for this reason alone it was interesting to watch Justice Lee read his decision via live stream on YouTube:…

    Read more …


Posted

in

, ,
Send this to a friend