The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Unfair contract terms, penalties & ACCC v Employsure 2020

    Unfair contract terms, penalties & ACCC v Employsure 2020

    When deciding whether a contractual term is unfair, a Court will likely consider if the term would cause a significant unbalance, if it is not reasonably necessary to protect legitimate interests, or if it would cause detriment.  Careful consideration should be given to the inclusion of clauses of this nature in standard form contracts, especially…

    Read more …

  • Updated USPTO guidelines on AI assisted inventions

    Updated USPTO guidelines on AI assisted inventions

    In response to the Biden administration’s Executive Order on the Safe, Secure, and Trustworthy Development and Use of Artificial Intelligence on 30 October 2023, which outlined policies and principles to promote responsible Artificial Intelligence innovation and competition, the United States Patent and Trademark Office (USPTO) issued inventorship guidance for artificial intelligence (AI) assisted inventions.  These…

    Read more …

  • Federal Court guidelines for e-discovery and metadata

    Federal Court guidelines for e-discovery and metadata

    Electronic discovery in the Federal Court of Australia (FCA) is nothing new.  From July 2014, the FCA began implementing the Court’s electronic court file (ECF) across its Australian registries.  This enabled the Court to embrace the use of technology in proceedings, including the use of electronic discovery, eLodgement, eTrials, eCourtroom, and video conferences.

    Read more …

  • Asset preservation orders – is dissipation a real risk?

    Asset preservation orders – is dissipation a real risk?

    An asset preservation order is a class of freezing order made by a Court usually without notice to the respondent or defendant (Exparte) for the purpose of preventing the frustration or inhibition of the Courts processes.  The need for an asset preservation order arises when there is danger that a judgment (or prospective judgement) made…

    Read more …

  • False and misleading representations – sections 29(1)(a)-(n) ACL

    False and misleading representations – sections 29(1)(a)-(n) ACL

    Where a business strays beyond mere “sales puffery” in promoting its goods or services and “crosses the line” in to the realm of deception, depending on the nature of the statements sections 29(1)(a)-(n) of Schedule 2 to the Competition and Consumer Act 2010 (Cth) (ACL) may be able to be used as a sword to…

    Read more …

  • Software developer obtains Court order – names behind IP addresses

    Software developer obtains Court order – names behind IP addresses

    Justice Burley of the Federal Court of Australia in the case of Siemens Industry Software Inc v Telstra Corporation Limited [2020] FCA 901 ordered that Telstra, within fourteen (14) days, provide to Siemens all documents in its control relating to the identity of certain Telstra Account holders.  Those account holders were suspected by Siemens of…

    Read more …

  • The © (copyright) symbol in use

    The © (copyright) symbol in use

    It is something that is often overlooked, however it is considered best practice to add a copyright statement and the little © symbol (Copyright Statement) on any literary or artistic works (Works) that a business publishes and asserts that it owns.  Under Australian law, the “material form” of all original Works is automatically protected by…

    Read more …

  • The Digital ID Bill 2023 (Cth) – key points

    The Digital ID Bill 2023 (Cth) – key points

    On 30 November 2023, the Digital ID Bill 2023 (Cth) and the Digital ID (Transitional and Consequential Provisions) Bill 2023 (Digital ID Bills) were introduced in the Australian Senate.  Digital IDs are designed to provide individuals with a convenient way to verify their identity when completing certain online transactions and dealing with government and certain…

    Read more …

  • The illegal phoenixing regime

    The illegal phoenixing regime

    The Treasury Laws Amendment (Combating Illegal Phoenixing) Act 2020 (Cth) (Amending Act) came into force on 18 February 2020 and was designed to prevent illegal phoenixing activity.  The Amending Act introduced reforms such as creditor-defeating disposition provisions to combat phoenixing activity.  Additional provisions amending the Corporations Act 2001 (Cth) were aimed to encourage accountability by…

    Read more …


Posted

in

, ,
Send this to a friend