Corporate law Brisbane

Failure to review contracts can cost millions…

HomePrivate: BlogCommercial lawCorporate lawFailure to review contracts can cost millions…

by

reviewed by

Malcolm Burrows

The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Misinformation and Disinformation Bill 2023 – draft insights

    Misinformation and Disinformation Bill 2023 – draft insights

    The Communications Legislation Amendment (Combatting Misinformation and Disinformation) Bill 2023 (Cth) (Misinformation Bill) was announced by the Department of Infrastructure, Transport, Regional Development, Communication and the Arts (DITRDCA) in January 2023.  The Misinformation Bill is aimed at restricting the flow of misinformation and disinformation by providing the Australian Communications and Media Authority (ACMA) with increased…

    Read more …

  • “User principle” damages in copyright breach cases

    “User principle” damages in copyright breach cases

    The usual position in intellectual property infringement matters is that the successful applicant can elect between an account of profits or damages.  However, what if the applicant has not suffered any direct loss as a result of the actions of the respondent that is held to have infringed its copyright?

    Read more …

  • What is an “earnout” clause in a business acquisition?

    What is an “earnout” clause in a business acquisition?

    An Earnout Right is further defined as any transaction in which an income-earning asset is sold for consideration that includes the creation of an ‘earnout right’ (Earnout Right) for the seller of the asset.

    Read more …

  • Paid family and domestic violence leave for small businesses

    Paid family and domestic violence leave for small businesses

    The Fair Work Amendment (Paid Family and Domestic Violence Leave) Act 2022 (Cth) (Amending Act) provides that employers must provide 10 days paid leave to all employees. Part-time and casuals also eligible. Confidentiality and ability to take leave in single and separate periods must be respected.

    Read more …

  • ACCC consultation environmental and sustainability guidance

    ACCC consultation environmental and sustainability guidance

    The Australian Competition and Consumer Commission releases Draft Guidance to help businesses make environmental and sustainability claims without misleading consumers. Seeking input from stakeholders to ensure guidance is effective and up-to-date with consumer law.

    Read more …

  • What are adequate cybersecurity measures?

    What are adequate cybersecurity measures?

    The adequacy of cyber security measures was considered in the case of Australian Securities and Investments Commission v RI Advice Group Pty Ltd [2022] FCA 496 (ASIC v Ri Advice Group).  One of the issues raised was whether the respondent had adequate cyber security and cyber resilience in place across its network of financial advisors. …

    Read more …

  • National Classification Scheme – proposed federal changes

    National Classification Scheme – proposed federal changes

    Albanese Government announces intention to reform National Classification Scheme, proposing R18+ for games simulating gambling and M for computer games with paid loot boxes/in-game purchases linked to chance. Learn more about proposed reforms and if simulated gambling needs to be addressed.

    Read more …

  • Misleading and deceptive conduct – Invisalign v SmileDirectClub

    Misleading and deceptive conduct – Invisalign v SmileDirectClub

    The case of Invisalign Australia Pty Limited v SmileDirectClub LLC [2023] FCA 395 (Invisalign v SDC) involved two (2) companies that offer what’s referred to as the “clear aligner teeth straightening treatment” (Clear Aligner).  On 23 December 2021, Invisalign Australia Pty Limited (Invisalign) commenced proceedings against SmileDirectClub Australia Pty Ltd and its US parent company…

    Read more …

  • Director’s absolute right to access company’s financial records

    Director’s absolute right to access company’s financial records

    Directors have a right to access financial records, but how far should they go? This article explores the balance between a director’s right to information and acting reasonably in circumstances.

    Read more …


Posted

in

, ,
Send this to a friend