The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Explaining Australia’s Media Bargaining Code

    Explaining Australia’s Media Bargaining Code

    The News Media Bargaining Code (NMBC) is quickly moving through Parliament and looks likely to become law. It requires digital platforms, such as Facebook and Google, to negotiate remuneration with News Companies for providing their media services. Non-compliance could result in hefty civil penalties.

    Read more …

  • The tort of injurious falsehood explained

    The tort of injurious falsehood explained

    Injurious falsehood is a tort which arises when false representations are made about a person or company, leading to damage. This article examines the key elements of the tort, including malice and actual loss, and looks at case law to explain them.

    Read more …

  • Review of QBCC decisions – pt 4

    Review of QBCC decisions – pt 4

    This article examines the nuances of the review process for a Queensland Building and Construction Commission (QBCC) notice to rectify defective domestic building work, explores a case study, and outlines the relevant takeaways. Learn more about how Queensland Civil and Administrative Tribunal (QCAT) can review a QBCC decision.

    Read more …

  • Review of QBCC decisions – pt 3

    Review of QBCC decisions – pt 3

    Queensland Civil and Administrative Tribunal cases have discussed the need for applicants to demonstrate cogent reasons for delay when seeking to review a Queensland Building and Construction Commission (QBCC) decision. This article explains the factors to consider for time extensions when internal and external reviews are being sought.

    Read more …

  • Kogan fined $310k for Spam Act breaches

    Kogan fined $310k for Spam Act breaches

    Kogan Australia Pty Ltd has been issued a hefty penalty and an enforceable undertaking for not complying with the Spam Act 2003 (Cth). Find out what this means for your business and what the consequences are for failing to comply.

    Read more …

  • Shareholder’s inspection allowed despite distrust

    Shareholder’s inspection allowed despite distrust

    Drafting Share Vesting Agreement requires consideration of several factors, including securities, copyright, class of shares, taxation, congruence with other agreements, and Events of Default. Alternatives to incremental vesting and requirements of Redeemable Preference Shares. Care must be taken when drafting Events of Default/Forfeiture clauses.

    Read more …

  • What exactly is the springboard doctrine?

    What exactly is the springboard doctrine?

    This article examines the ‘springboard’ doctrine which refers to the benefit that is derived because of misuse of confidential information by a defendant that enables them to ‘springboard’ a new product or service to market more rapidly than if they had used their own mind.

    Read more …

  • Review of QBCC decisions – pt 2

    Review of QBCC decisions – pt 2

    Under the Queensland Building and Construction Commission Act 1991 (Act) the Queensland Building and Construction Commission (QBCC) is empowered to make a variety of decisions such as but not limited to:

    Read more …

  • Review of QBCC decisions – pt 1

    Review of QBCC decisions – pt 1

    Understand your rights when it comes to challenging a decision made by the Queensland Building and Construction Commission (QBCC). Learn more about the Act and the time limits for seeking a review with the Queensland Civil and Administrative Tribunal (QCAT).

    Read more …


Posted

in

, ,
Send this to a friend