The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Assigning intellectual property and the right to sue

    Assigning intellectual property and the right to sue

    This case examines Re Taypar Pty Ltd v Benko Santic [1989] FCA 543, which determined that an assignee of intellectual property rights cannot sue for pre-assignment infringements, unless the assignment explicitly assigns a right to do so.

    Read more …

  • Overview of negligence claims in domestic building disputes

    Overview of negligence claims in domestic building disputes

    A domestic building contract gone wrong: Cerda v Jacob [2020] QCATA 57 highlights the difficulties homeowners face when contracts don’t comply with the Queensland Building and Construction Commission Act (Qld) 1991, leading to issues with enforcing the contract and asserting rights to quality works or remedy defective construction.

    Read more …

  • Ending a domestic building contract

    Ending a domestic building contract

    Ending a domestic building contract can be complicated. Discover the requirements for a home warranty insurance claim and the implications of the Harper Property Builders Pty Ltd v Queensland Building and Construction Commission [2018] QCATA 70. Find out how to navigate a building contract “divorce” with good faith.

    Read more …

  • Think twice before claiming delay due to COVID-19

    Think twice before claiming delay due to COVID-19

    In response to COVID-19, the Federal Court of Australia has adopted virtual proceedings and is reluctant to grant stays or adjournments. Read this article to learn more about the Court’s view and the pros and cons of virtual trials.

    Read more …

  • Evidence from the Wayback Machine accepted

    Evidence from the Wayback Machine accepted

    Australian Courts are increasingly considering the use of evidence from the Wayback Machine, but questions remain as to whether they will accept such reports in practice and what will be allowed?

    Read more …

  • Arbitration clauses in building disputes

    Arbitration clauses in building disputes

    The QCAT decision of 4D Electrical Qld v Greyburn Pty Ltd [2020] QCAT 74 shows arbitration can be a more efficient alternative to Court/tribunal litigation. Courts uphold contractual obligations agreed to by parties, proving arbitration is a viable option.

    Read more …

  • Particulars – their importance in civil litigation

    Particulars – their importance in civil litigation

    This article provides an overview of the Federal Court’s rules and procedures for preliminary discovery, which allows potential applicants to determine if there is a good cause of action before filing a claim. Learn how to navigate the process and understand the Court’s expectations.

    Read more …

  • COVID-19 relief measures for companies

    COVID-19 relief measures for companies

    The Federal Government has passed a package of temporary measures to support businesses and relieve financial distress during the COVID-19 pandemic. Find out how these measures could affect your business and what you need to know.

    Read more …

  • $750k awarded for fake online reviews

    $750k awarded for fake online reviews

    The Supreme Court of South Australia awarded $A750,000 in damages to a lawyer in the case of Cheng v Lok [2020] SASC 14, demonstrating the serious consequences of posting fake reviews online. Find out more about the implications of this case and alternative legal actions for companies that receive negative reviews.

    Read more …


Posted

in

, ,
Send this to a friend