Failure to review contracts can cost millions…

HomePrivate: BlogCommercial lawCorporate lawFailure to review contracts can cost millions…

by

reviewed by

Malcolm Burrows

Reading Time:

4–5 minutes

The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Are your website’s terms and conditions legally binding?

    Are your website’s terms and conditions legally binding?

    Online contracts have legal implications and must adhere to consumer protection regulations. The Australian case of eBay International AG v Creative Festival Entertainment Pty Limited (ACN 098 183 281) [2006] FCA 1768 highlights the importance of understanding these regulations when drafting online contracts.

    Read more …

  • Without Prejudice privilege – Australian law

    Without Prejudice privilege – Australian law

    This article explores the legal implications of using the term “without prejudice” in commercial negotiations. Discover the source of the law, common law exceptions, and what attaching the term to correspondence may mean.

    Read more …

  • What exactly is a Corporate Governance Framework?

    What exactly is a Corporate Governance Framework?

    Businesses need to ensure their advertising and marketing materials comply with the Australian Consumer Law (ACL). Our experienced team can provide advice on structuring promotions, drafting terms and conditions, and obtaining permits for competitions and games of chance, helping businesses avoid costly penalties from the Australian Competition and Consumer Commission (ACCC).

    Read more …

  • Director’s duty to prevent insolvent trading

    Director’s duty to prevent insolvent trading

    This article provides an overview of directors’ duty to prevent insolvent trading under the Corporations Act 2001 (Cth), including the test for solvency, indicators of potential insolvency, and potential defences.

    Read more …

  • Shifts in criminal liability for company officers

    Shifts in criminal liability for company officers

    The Personal Liability for Corporate Fault Reform Act 2012 (Cth) was implemented to ensure personal criminal liability for corporate fault is imposed in line with corporate governance principles, reducing risk and compliance issues for Company Officers.

    Read more …

  • Thumbs down to McDonald’s “send to friend” campaign

    Thumbs down to McDonald’s “send to friend” campaign

    Businesses should be aware of their legal obligations when using ‘send to friends’ facilities to avoid potential liability for breach of anti-spam laws. Find out how one company faced legal action for failing to comply with the Spam Act 2003 (Cth).

    Read more …

  • Why is a Privacy Act Compliance Audit (PACA) necessary?

    Why is a Privacy Act Compliance Audit (PACA) necessary?

    Understand the implications of the Privacy Act 1988 (Cth) and national privacy principles with the upcoming legislative amendments. Find out what a Privacy Act Compliance Audit (PACA) involves, who should consider it, and the consequences of non-compliance.

    Read more …

  • How will the new Privacy laws affect your organisation?

    How will the new Privacy laws affect your organisation?

    What were the changes to the Privacy Act in 2014? Legislative changes to the Privacy Act 1988 (Cth) (Privacy Act) will come into effect on 12 March 2014.  The Privacy Amendment (Enhancing Privacy Protection) Act 2012 (Cth) (Amendments) amends the Privacy Act by introducing:

    Read more …

  • Agile software development contractual issues

    Agile software development contractual issues

    This article examines Agile Contracts, legally binding agreements that outline roles and responsibilities for software development projects using Agile methodology. It covers key decisions, such as parties, payment milestones, warranties, and other considerations like gain sharing and budget escrow.

    Read more …


Posted

in

, ,
Send this to a friend