The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Advertising guide for carriage service providers released

    Advertising guide for carriage service providers released

    Carriage Service Providers must follow the Telecommunications Consumer Protections Code 2019 when advertising their offers to consumers. Learn the key elements to include, the advertising medium, and the use of disclaimers to avoid financial and reputational risks. Read this article to find out more.

    Read more …

  • Standard form telecom services agreements

    Standard form telecom services agreements

    Carriage service providers must comply with a range of legal requirements to protect their customers and their business. Learn what these are and how to ensure your company meets them in this informative article.

    Read more …

  • Revisiting software as a service agreement

    Revisiting software as a service agreement

    Discover the legal considerations of commercialising a SaaS (Software-as-a-Service) Agreement as a business model. Uncover the key issues to consider when going to market with a SaaS offering, such as subscription terms, service levels, data handling, intellectual property (IP) in customizations, and more.

    Read more …

  • Managed service agreements for IT businesses

    Managed service agreements for IT businesses

    A Managed Services Agreement (MSA) outlines the roles and responsibilities of IT services provider and client, detailing services, payment, security, and more. It helps mitigate risks and ensure both parties are clear on expectations.

    Read more …

  • When to complain about domestic building work

    When to complain about domestic building work

    MacFarlane v QBCC [2019] QCAT 408 highlights the need to understand and adhere to time limits in Queensland Building and Construction Commission Act 1991 to preserve rights to compensation and direction to rectify defective domestic building work.

    Read more …

  • Director’s identification numbers to become a reality

    Director’s identification numbers to become a reality

    On 12 June 2020, the Treasury Laws Amendment (Registries Modernisation and Other Measures) Act 2020 introduced the requirement for all Australian company directors to have a “Director Identification Number” (DIN).  The DIN will become a single identifier for each director across all of their office holdings with the true identity of each director is verified…

    Read more …

  • What are software licence agreements?

    What are software licence agreements?

    A Software Licence Agreement (SLA) is a contract between two parties granting the right to use software. Learn more about common clauses, legal issues, and how to protect yourself when drafting the agreement.

    Read more …

  • Directions to rectify defective domestic building work – part 1

    Directions to rectify defective domestic building work – part 1

    Understand the timeframes and importance of making a complaint to the Queensland Building and Construction Commission Act 1991 (Qld). Find out more about the checks and timeframes that protect home owners when making a major financial decision.

    Read more …

  • Top 11 legal tips for selling a technology business

    Top 11 legal tips for selling a technology business

    These tips include asset sale or share sale, intellectual property ownership, legal and accounting due diligence, change of control issues, restraint of trade clauses, key personnel, and more.

    Read more …


Posted

in

, ,
Send this to a friend