Failure to review contracts can cost millions…

HomePrivate: BlogCommercial lawCorporate lawFailure to review contracts can cost millions…

by

reviewed by

Malcolm Burrows

The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Is using a trade mark in AdWords considered infringement?

    Is using a trade mark in AdWords considered infringement?

    A Court concluded that a company had infringed a trade mark using Google AdWords in Veda Advantage Limited v Malouf Group Enterprises Pty Limited [2016] FCA 255. Click through to learn more about the dispute, and the learning points and takeaways.

    Read more …

  • Be cautious when alleging patent infringement

    Be cautious when alleging patent infringement

    The Court weighed in on the issue of unjust threats of patent infringement and the damages that may be payable. Learn more about the importance of proving direct causation between the threat and the loss, and the implications for patent holders and infringers alike.

    Read more …

  • What are end user licence agreements?

    What are end user licence agreements?

    Understand the legal risks of end-user license agreements (EULAs): learn about the common clauses, conditions, and warranties that can protect both the licensee and the licensor. Find out how to ensure your EULA is legally sound.

    Read more …

  • Federal Court rules on unfair contract clauses

    Federal Court rules on unfair contract clauses

    This case serves as a reminder to businesses and consumers to review their contracts and ensure they are compliant with the Australian Consumer Law (ACL). Find out more about the Federal Court ruling and what it means for businesses and consumers.

    Read more …

  • Copyright infringement for computer code

    Copyright infringement for computer code

    Computer code is automatically protected by copyright. Unauthorised reproduction of it may constitute an infringement, as illustrated by two federal cases. To understand copyright infringement with respect to computer code, read “Who owns the code?”

    Read more …

  • Discovery process in the Federal Court of Australia

    Discovery process in the Federal Court of Australia

    Discover the process for seeking documents in the Federal Court of Australia. Learn about the roles of the parties, criteria for standard and non-standard discovery, and the process of giving discovery. Get the full details on the Federal Court Rules 2011 and its revised regime for discovery.

    Read more …

  • Patents, grace periods and revocation explained

    Patents, grace periods and revocation explained

    Disclosure of an invention prior to applying for a patent can have serious implications. Learn more from Dundas Lawyers to understand the important considerations, including the twelve (12) month grace period and its effect on revocation.

    Read more …

  • The importance of evidence

    The importance of evidence

    This article explores the different types of evidence and their importance in civil and intellectual property litigation. Learn more about the rules of evidence and how they apply to your case by reading the full article.

    Read more …

  • Who holds ownership of the code?

    Who holds ownership of the code?

    Understand who owns the computer code used in software development projects. Consider employee or contractor engagement, joint ownership, and assignment of copyright to ensure your project is protected.

    Read more …


Posted

in

, ,
Send this to a friend