The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Should a lawyer be the Lead Consultant?

    Should a lawyer be the Lead Consultant?

    Discover the role of a Lead Consultant in a business acquisition process and the qualities needed for success. Gain insight from case studies and find out the legal advice you should obtain for your own situation.

    Read more …

  • Working with an Expert Adviser

    Working with an Expert Adviser

    Expert advisors may be consulted for business acquisitions, including IT consultants, industry experts, insurance brokers, scientists, lawyers, and patent attorneys. Advisory team must understand role, scope of work, and due date for successful work.

    Read more …

  • Getting confidentiality agreements in place

    Getting confidentiality agreements in place

    Part 5 – Planning a business acquisition Confidentiality Agreements (Confidentiality Agreement or NDA’s) are essential in business Acquisitions, particularly if either the Target or Acquirer is subject to the ASX Listing Rules. Whilst generally an equitable obligation of confidence is applicable, a Confidentiality Agreement reduces the obligations of the parties to writing to ensure that…

    Read more …

  • Preparing staff and others for due diligence

    Preparing staff and others for due diligence

    This article explores the scope of initial due diligence, roles and responsibilities of an Advisory Team, considerations for retained employees, and the importance of project management in the acquisition process. Plus, a disclaimer and contact information for a legal practice director.

    Read more …

  • Pre-acquisition planning – shares or assets?

    Pre-acquisition planning – shares or assets?

    Planning a business acquisition? Consider structure, ownership, securities, contract and assets. Generally, asset purchase or security acquisition? Don’t forget to factor in the Target’s wishes.

    Read more …

  • Selecting a business valuation methodology

    Selecting a business valuation methodology

    Are you considering a business acquisition? Learn three methods of valuation and which are best for businesses with high asset values, those that are not profitable, and those valued on a going concern basis. Read this article from RSM Bird Cameron Chartered Accountants to find out more.

    Read more …

  • Should you work in the industry before you buy?

    Should you work in the industry before you buy?

    Are you considering a business acquisition? Learn how working in the business can help verify takings and the importance of a tuition period in the Real Estate Institute of Queensland (REIQ) Business Sale Contract. Click through to find out more.

    Read more …

  • How to identify fraudulent workers’ comp claims

    How to identify fraudulent workers’ comp claims

    Learn how to identify and prevent Worker’s Compensation fraud with this article. Employees found guilty of fraud face criminal convictions, fines up to $55,000 and a max of five (5) years imprisonment.

    Read more …

  • Electronic service of legal documents

    Electronic service of legal documents

    The decision in Conveyor & General Engineering Pty Ltd v Basetec Services Pty Ltd [2014] QSC 30 examined validity of service of documents via email and Dropbox. Find out judgement and “take-aways” to help navigate complex legal process of document service.

    Read more …


Posted

in

, ,
Send this to a friend