The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Retention of title clauses in commercial contracts – why they matter

    Retention of title clauses in commercial contracts – why they matter

    Understand the implications of a retention of title clause and learn about the Perfected Purchase Money Security Interest. Find out what to do if goods become commingled, the effects of not registering on the Personal Property Securities Register (PPSR), and the benefits of registration. Click through to learn more.

    Read more …

  • When is a licensee really a franchisee?

    When is a licensee really a franchisee?

    This article dives into the details of franchisor/distributorship relationships, exploring elements, examples, and control needed to determine the distinction. Get insight into what constitutes a system or marketing plan, and learn what type of ‘helpful suggestions’ qualify.

    Read more …

  • User posts can be advertisements!

    User posts can be advertisements!

    The Advertising Standards Board upholds the Code of Ethics for advertising and marketing communications. Decisions included user comments on social media being subject to the Code. Advertisers must take extra care to comply.

    Read more …

  • Employee or contractor – impact on intellectual property

    Employee or contractor – impact on intellectual property

    This article explores the legal implications of determining whether an individual is an employee or contractor. Learn how a multi-factor test can help to identify the correct status, and understand the potential impact on intellectual property.

    Read more …

  • Appointing an alternate director explained

    Appointing an alternate director explained

    Appointing an Alternate Director? Understand the powers and responsibilities with our obligation free and confidential discussion. Learn more now.

    Read more …

  • Copyright in artistic works – Australian law

    Copyright in artistic works – Australian law

    Discover how copyright law protects artistic works and what to consider when reproducing them. Learn about the implications of ownership, what constitutes ‘substantial’ infringement, and how to get permission or licence a copyright.

    Read more …

  • Guide for managing data breaches

    Guide for managing data breaches

    Parliament introduced the Data Breach Bill 2016, which will make notifications of data breaches mandatory. Learn more about the Bill and obligations of organisations to protect personal info in our article.

    Read more …

  • Failure to review contracts can cost millions…

    Failure to review contracts can cost millions…

    The case of The State of NSW v UXC Limited [2011] NSWCS 530 serves as a reminder of the need for organisations to pay close attention to contract details. An oversight can result in costly damages.

    Read more …

  • Is your business ready for investors?

    Is your business ready for investors?

    Want to attract investors? This article reveals the essential steps to make your business “investor ready.” From crafting a solid business plan to securing legal certainty, learn how to prepare your business for successful investment and stand out to potential backers.

    Read more …


Posted

in

, ,
Send this to a friend