The case of The State of NSW v UXC Limited [2011] NSWCS 530 demonstrates the need for organisations to play close attention to the minute details in their contracts.  As time is of the essence in most business transactions quite often the contract details frequently get overlooked.  In this instance the State of NSW was awarded $2,594,063.00 in damages and $126,185.14 in interest plus costs because a clause in the Contract schedule remained silent as to the limitation of the amount that could be awarded for lawful termination.

Background

The State of NSW released a Request for Tender (RFT) in 2007 for the replacement of the core computing system for the NSW Registry of Births, Deaths and Marriages unit of the Attorney-Generals’ Department (Plaintiff).  Subsequently, pursuant to the RFT the Plaintiff contracted with UXC Limited (Defendant) in 2008 pursuant to a written contract (Contract).  As a part of the Contract a dispute resolution clause was included that stipulated that all disputes that arose which could not be resolved by negotiation were to be resolved by the appointment of an independent expert chosen by the Plaintiff and Defendant.  A dispute subsequently arose concerning the Plaintiff’s right to terminate the Contract for the Defendant’s breach and the damages for which the Plaintiff was entitled to claim.

The expert determined that the Plaintiff was entitled to terminate the Contract and to recover damages; however the Defendant commenced proceedings based upon the presumption that the dispute resolution clause was unenforceable as clause 9 of schedule 5 of the Contract stipulated that Court proceedings could be pursued only if the amount awarded by the expert exceeds the amount in clause 8 of schedule 5.  No amount was listed in item 8 of schedule 5 which was an oversight when drafting and reviewing the Contract.

The question for the Court was whether the Defendant could bring legal proceedings pursuant to a clause that was based upon on an unknown number, or based upon a number that could be determined by referencing the original RFT.

Submissions by the Plaintiff

  • that clause 10 of schedule 5 provides that a party must treat the determination of the expert as final and binding unless there is a right to commence legal proceedings pursuant to clause 9;
  • in this case no right is given since clause 9 only pertains to legal proceedings where the amount of damages determined by the expert exceeds the amount in clause 8 of schedule 5; and
  • there is no amount stipulated in clause 8 of schedule 5 for the purpose to which clause 9 of schedule 5 could operate.

Submissions by the Defendant

The submissions made on behalf of the Defendant that:

  • there was an intention that an amount in item 8 of Schedule 1 for the purposes of clause 9 of Schedule 5 be listed but was overlooked;
  • therefore, in those circumstances, the intention was that their agreement that was recorded in the RFT tender response should apply;
  • clause 4.12 of part E of the RFT stated that, apart from some specific terms referred to, the terms included in the user guide apply; and
  • part B13 of the user guide provides that an expert determination amount are $250,000 for contracts valued at contracts less than $50 million and $1 million for a contract valued at more than $50 million.

Decision

Ball J concluded and found that:

  • the parties had an enforceable right to impose a condition that they submit their dispute to arbitration (Scott v Avery [1856] EngR 810);
  • the decision of the expert is binding;
  • the limit of liability under the Contract was $5 million, therefore the parties did not specify a threshold amount above the amount awarded by the expert, and to which they were entitled to commence Court proceedings;
  • the limit of liability of $5 million barred any proceedings for awards less than that amount; and
  • clause 9 of schedule 5 has no effect as the parties failed to specify an amount in clause 8 of schedule 5 that would trigger its operation.

Therefore the Defendant was ordered to pay:

  • $2,594,063.00 in damages; and
  • interest in the amount of $126,185.14 plus costs.

This case is a reminder that careful attention needs to be taken when drafting contracts.  This is especially the case when using standard form contracts as details can be overlooked that could end up being costly.

Although the drafting of contracts can be more time efficient when using standard form contracts the result can be dire.  Quite often contract schedules are overlooked in comparison to the major terms of the contract; however, often contract schedules contain important information that directly relate to how a term of the contract is to be interpreted.  In this case, what could have amounted to a payment of damages in the amount of $250,000 ended up costing millions.

Careful attention to detail in drafting cross-references is critical in making sure that this scenario does not happen to you.

Further information

Dundas Lawyers regularly drafts various different critical contracts.  To ascertain how Dundas Lawyers can assist you, contact us for a confidential and obligation-free discussion:


Related insights about corporate law

  • Terminating an employee for serious misconduct

    Terminating an employee for serious misconduct

    These tips include asset sale or share sale, intellectual property ownership, legal and accounting due diligence, change of control issues, restraint of trade clauses, key personnel, and more.

    Read more …

  • The 20/12 Rule & anti-avoidance provisions

    The 20/12 Rule & anti-avoidance provisions

    This article examines Chapter 6D of the Corporations Act 2001 (Cth) (Act) and its implications for raising capital in Australia without issuing a formal disclosure document. It looks at Australian Securities and Investments Commission (ASIC)’s powers of exemption and anti-avoidance.

    Read more …

  • Federal Circuit Court strikes down ‘no refunds’ clause

    Federal Circuit Court strikes down ‘no refunds’ clause

    In a recent judgment (Ferme v Kimberley Discovery Cruises Pty Ltd [2015] FCCA 2384), the Federal Circuit Court held that a term of a cruise company’s standard conditions, which allowed the company to cancel a cruise for a wide range of reasons without giving any refunds to its passengers, was an ‘unfair term’ under the…

    Read more …

  • Underpaying employees can have serious consequences

    Underpaying employees can have serious consequences

    Employers have been accused of underpaying their employees and falsifying payroll records. Learn more about how the Fair Work Act 2009 (Cth) safeguards employees and how businesses can ensure they are compliant.

    Read more …

  • Data security – the increasing burden

    Data security – the increasing burden

    The consequences for an Australian business victim for a breach of cyber security are forecast to exponentially increase. In February 2015 the Parliamentary Joint Committee on Intelligence and Security (Committee) recommended the introduction of mandatory data breach notification scheme (Scheme) by the end of 2015.[1] Whilst the details of the incoming Scheme are currently scant,…

    Read more …

  • Intellectual property theft and employee information theft

    Intellectual property theft and employee information theft

    Leica Geosystems Pty Ltd v Koudstaal (No 3) [2014] FCA 1129 (Leica Geosystems) is a notable court case involving an Anton Piller order and employee theft. Find out more about what this means for companies and their intellectual property rights.

    Read more …

  • Revenge porn – legal options

    Revenge porn – legal options

    Revenge porn (Revenge Porn) refers to sexually explicit media that is distributed without the consent of the individual(s) involved.[1]  An act of Revenge Porn therefore involves the recording of video or still images of a person that is usually engaged in sexual acts (Revenge Content) and publishing or threatening to publish it.  A person’s participation…

    Read more …

  • What exactly is an advertising sign-off?

    What exactly is an advertising sign-off?

    Injunctions are Court orders that can restrain almost any conduct. Prohibitory, Mandatory, and Ex Parte injunctions can be sought if serious question to be tried, urgency, damages would not suffice, and the balance of convenience favours the applicant.

    Read more …

  • Productivity Commission publish report on the Workplace Relations Framework

    Productivity Commission publish report on the Workplace Relations Framework

    The Productivity Commission has released a draft report on the workplace relations framework, with suggestions that could affect penalty rates, minimum wages, and unfair dismissal. Learn more about the proposed changes and have your say.

    Read more …


Posted

in

, ,
Send this to a friend